Personal tools
You are here: Home Case Studies The Charlesworth Group

The Charlesworth Group

Monday October 26, 2009 13:39 PM

The Charlesworth Group, based in Wakefield, used MAS for expert help to streamline its processes, reduce machine downtime and improve stock control and on-time delivery.

As a result of two 10 day manufacturing improvement projects, the company has achieved the following:

  • The average time to generate an estimate has
    been cut by 50%.
  • A 40% reduction in waste has been achieved.
    Sales have been boosted by £90k.
  • 15 employees have been trained to become
    ‘super-users’ in manufacturing planning
    techniques.
  • 3 jobs have been safeguarded, which may other
    wise have been under threat.
  • On-time delivery has improved by 10%.


“The results of the MAS intervention have been impressive and far reaching. For example, we have removed the need to have a separate warehouse to store large amounts of paper stock. We are now much more efficient and able to estimate our requirements more accurately which has improved cash flow and the amount of spoilage has been massively reduced.”

David Boothman, Managing Director

Click here to download the full case study.

Document Actions